November 18, 2026Las Vegas 52°F · Mostly SunnyNewsletterSend a tip

Local reporting on the decisions that change daily life in the valley

Water & Environment · Nevada

Desert Research Institute scientists say Nevada data centers could need up to 12,800 more acre-feet of water a year

Desert Research Institute researchers updated their estimate of data center water use after NV Energy raised its power forecast. They say limited site data leaves the true figure uncertain.

Listen to this brief · 5 min

Read aloud by an AI voice from the text below. Download MP3

Water & Environment illustration for: Nevada Data Centers' Water Needs Hard to Pin Down, DRI Says
Water & Environment · Illustration by News In Las Vegas

What happened

Two scientists at the Desert Research Institute (DRI) have released an updated report estimating how much water Nevada's growing number of data centers may need, The Nevada Independent reported. The researchers said the answer depends heavily on cooling technology and on how the power for those centers is produced.

According to The Nevada Independent, more than 75 data centers are operating, under construction or planned across the state, mostly in the Las Vegas and greater Reno areas. Sean McKenna, executive director of DRI's division of hydrologic sciences, told the outlet, "We don't know how water-efficient these places are going to be."

Why the numbers had to be redone

McKenna and Erik Henzl, a DRI research scientist and environmental economist, spent more than a year linking projected power needs to water use for data centers not yet built. Their first report came out in January and was described as the first comprehensive Nevada-specific look at data centers' water and power needs.

A much larger power forecast

That January report relied on NV Energy's 2024 Integrated Resource Plan, which listed 12 data center projects seeking 5,900 megawatts (MW) by 2033. The Nevada Independent reported that the utility's 2026 plan, released this spring, listed more than three dozen data centers seeking 16,530 MW by 2036.

Data centers now account for 5 percent of NV Energy's sales and are expected to reach 64 percent by 2046, according to the outlet. The DRI report says NV Energy expects to serve loads about 2.5 times current levels by 2046. For more on the utility, see our recent coverage of NV Energy's rate plans.

What the new estimates show

Assuming medium or low water consumption, the researchers found Nevada would need an additional 4,200 to 12,800 acre-feet of water per year under NV Energy's updated forecast. The Nevada Independent reported that the high end is roughly what Carson City's businesses and 58,000 residents use in a year.

Direct and indirect use

Under a medium-usage model, direct water use at proposed data centers could grow to nearly 12,800 acre-feet per year. Indirect use, meaning water used off-site to generate their power, could rise to nearly 22,000 acre-feet. Because NV Energy imports most of the state's power, part of that indirect burden would fall on out-of-state energy producers.

Las Vegas-area examples

Cooling methods vary with a facility's age, local rules such as Southern Nevada's ban on evaporative cooling, and other factors. Novva's 100 MW Las Vegas data center uses a closed-loop system and used less than 2 acre-feet of water in 2025, the outlet reported. Google's Henderson data center uses evaporative cooling and used about 636 acre-feet in 2024.

Gaps in the data

The researchers said individual facility water use is largely not public, so they had to work from estimates. "The water demand is more difficult to assess because of a dearth of information," Henzl told The Nevada Independent. McKenna called the limited site-specific data "really a frustration with this report."

On-site power adds uncertainty

NV Energy's 2026 plan proposes nearly 12,000 MW of new generation, mainly solar, battery storage and natural gas, with some geothermal, but that falls short of total demand. Some developers are turning to behind-the-meter power generated on-site, which bypasses many state regulatory requirements. Water needs for that power depend on the source, since solar uses little water and natural gas uses more. More on the state's supply is in our water coverage.

What to watch next

  • NV Energy's 2026 Integrated Resource Plan, which proposes nearly 12,000 MW of new power generation.
  • Whether the more than three dozen data centers seeking 16,530 MW by 2036 use newer, water-efficient cooling.
  • Behind-the-meter power projects for data centers, whose water use depends on the energy source.
  • Where imported power comes from, which the researchers called a big unknown for indirect water use.
Section graphic: Water & Environment in the Las Vegas valley
More water & environment coverage: see all stories

Trending in Vegas

  1. Small Nevada Gaming Operators Face Fines, License LossCommunity · Nevada
  2. Las Vegas Home Listings Hit 10-Year High as Sales SlowReal Estate · Valley-wide
  3. Nevada Bids to Host NASA's Future US Space AcademyDevelopment · Nevada
  4. Assemblymember Torres-Fossett Resigns After ReelectionElections · Valley-wide
  5. Sun Youth Forum: CCSD Students Earn $35,000 in ScholarshipsSchools · Valley-wide

Get Las Vegas news in your inbox

The day's top local briefs every morning at 7:30, each linked to the newsroom that reported it.

Know more about this story?

If you were there, work on the project or have documents, tell us. Tips are read by a person and checked before anything is published.