Grand Prix track teardown brings lane closures on the Strip, Koval, Harmon and Sands this week as crews work toward Dec. 24
Crews began dismantling the 3.8-mile Formula 1 circuit after Saturday's race, and work will continue through Dec. 24. Here are the lane closures drivers should expect on the Strip, Koval, Harmon and Sands this week.
Listen to this brief · 4 min
Read aloud by an AI voice from the text below. Download MP3

What happened
Crews started taking apart the Formula 1 Las Vegas Grand Prix street circuit right after the 50-lap race ended late Saturday night, the Las Vegas Review-Journal reported. Max Verstappen won the race, the fourth annual edition of the event. The 3.8-mile track runs mostly on Las Vegas Boulevard, Koval Lane, Harmon Avenue and Sands Avenue.
According to the Review-Journal, crews will keep removing the pieces of the street circuit through Christmas Eve, returning the Strip and nearby streets to normal. The newspaper outlined the lane closures motorists can expect this week as the removal of race infrastructure begins.
Closures drivers should expect this week
Las Vegas Boulevard
From Monday through 11:59 p.m. Wednesday, Las Vegas Boulevard is down to one lane in each direction between Spring Mountain Road and Harmon Avenue while crews pull out track barriers, the Review-Journal reported. Farther north, two southbound lanes between Fashion Show Drive and Spring Mountain Road are scheduled to close from 12:01 a.m. to 9 a.m. daily, Tuesday through Nov. 30. The newspaper also listed Nov. 25 and Nov. 30 specifically as dates for those overnight southbound closures.
Koval Lane and Harmon Avenue
Koval Lane will be fully closed between Harmon Avenue and Rochelle Avenue from 7 a.m. to 5 p.m. daily, Monday through Wednesday, according to the Review-Journal. A single lane is set to reopen each day from 5 p.m. to 7 a.m. On Tuesday and Wednesday, periodic two-lane closures are planned on Koval between Rochelle and Westchester Drive as crews take down gantries.
Harmon Avenue will also see gantry work. Between 9 a.m. Monday and 9 a.m. Tuesday, drivers should expect periodic lane closures on Harmon between Las Vegas Boulevard and Koval Lane, the newspaper reported.
Sands Avenue
On Sands Avenue, one lane in each direction between Las Vegas Boulevard and Manhattan Street will be open 24/7 through 9 p.m. Wednesday, the Review-Journal reported. Sands is one of the four main roads the 3.8-mile circuit uses, along with Las Vegas Boulevard, Koval Lane and Harmon Avenue.

Bellagio work and the Thanksgiving pause
Crews are also beginning to dismantle the Bellagio Fountain Club, with that work running through Dec. 24. The two-lane and sidewalk closure in front of Bellagio will remain in place during that time, according to the Review-Journal.
No track dismantling is scheduled over Thanksgiving weekend, Thursday through Saturday, the newspaper reported. For earlier coverage of the cleanup, see this report on teardown closures affecting Strip lanes, bridges and bus stops.
Longer-term changes to setup and teardown
Las Vegas Grand Prix and Clark County officials are in talks about further streamlining how race infrastructure is set up and taken down, the Review-Journal reported. A new 10-year deal for the race takes effect next year.
With that deal coming, plans are underway to add permanent race infrastructure pieces around the 3.8-mile circuit, according to the newspaper. The Review-Journal did not say which pieces would become permanent or when they would be installed.
What to watch next
- Overnight closures of two southbound Las Vegas Boulevard lanes between Fashion Show Drive and Spring Mountain Road, scheduled from 12:01 a.m. to 9 a.m. through Nov. 30.
- Dismantling of the Bellagio Fountain Club and the two-lane and sidewalk closure in front of Bellagio, set to continue through Dec. 24.
- Results of talks between Las Vegas Grand Prix and Clark County officials on streamlining race setup and teardown.
- Plans to add permanent race infrastructure around the circuit as the new 10-year deal begins next year.